The VMware 3V0-42.20 Exam is a vendor-neutral certification exam that is recognized globally. This certification is highly valued in the IT industry and is considered as a benchmark for the IT professionals. The certification holders are recognized as the experts in the NSX-T Data Center solution and are highly sought after by the organizations.
NEW QUESTION # 19
An architect is helping an organization with the Physical Design of an NSX-T Data Center solution. This information was gathered during a workshop about ESXi Host networking:
A total of 50 ESXi hosts to be configured as Transport Nodes.
All ESXi hosts have a dedicated 2 X Intel 10Gbps Physical Network adapter for the Overlay Traffic.
To achieve low latency, high throughput, redundancy, and performance, which two NIC teaming policies should the architect recommend? (Choose two.)
- A. Load Balance Source
- B. Failover Order
- C. Load Balance Port ID
- D. Load Balance Source MAC
- E. Load Balance Source Port ID
Answer: A,D
Explanation:
Uplink profiles within NSX-T shows that you can only use Load balance Source and Load balance Source MAC, failover order doesnt provide any load balancing or high throughput https://docs.vmware.com/en/VMware-NSX-T-Data-Center/3.1/installation/GUID-50FDFDFB-F660-4269-9503-39AE2BBA95B4.html
https://docs.vmware.com/en/VMware-NSX-T-Data-Center/3.2/installation/GUID-50FDFDFB-F660-4269-9503-39AE2BBA95B4.html Failover Order: Select an active uplink is specified along with an optional list of standby uplinks. If the active uplink fails, the next uplink in the standby list replaces the active uplink. No actual load balancing is performed with this option. Load Balance Source: Select a list of active uplinks. When you configure a transport node, you can pin each interface of the transport node to one active uplink. This configuration allows use of several active uplinks at the same time. Load Balance Source MAC Address: Select an uplink based on a hash of the source Ethernet.
NEW QUESTION # 20
A customer wants to use ECMP to provide additional throughput and availability for their critical business applications. Some applications require load balancing for scale and availability.
Which two Edge design choices can an architect present to the customer? (Choose two.)
- A. Create a Tier-0 gateway in Active/Active mode and a Tier-1 gateway in Active/Standby mode.
- B. Create a Tier-0 gateway in Active/Standby mode and a Tier-1 gateway in Active/Standby mode.
- C. Configure ECMP and Load Balancing on the Tier-0 gateway.
- D. Configure ECMP on the Tier-0 gateway and Load Balancing on the Tier-1 gateway.
- E. Create a Tier-0 gateway in Active/Standby mode.
Answer: C,E
NEW QUESTION # 21
Which three assessment findings are part of a Conceptual Design? (Choose three.)
- A. justifications
- B. assumptions
- C. vendor model
- D. constraints
- E. host names
- F. risks
Answer: B,D,F
NEW QUESTION # 22
What selection is the key design benefit provided by a dedicated Edge Cluster VM or Bare Metal? (Choose the best answer.)
- A. predictable network performance
- B. multiple Tier-0 gateways per Edge Node Cluster
- C. reduced administrative overhead
- D. support for Edge Node Clusters with more than 10 Edge Nodes
Answer: A
NEW QUESTION # 23
Which three assessment findings are part of a Conceptual Design? (Choose three.)
- A. justifications
- B. vendor model
- C. constraints
- D. host names
- E. risks
- F. assumptions
Answer: A,C,E
NEW QUESTION # 24
An architect is helping an organization with the Logical Design of an NSX-T Data Center solution.
This information was gathered during the Assessment Phase:
Maximum performance and availability is required between the physical and virtual network.
Load Balancing service is required for back-end web servers.
NAT is required.
Which selection should the architect include in their design? (Choose the best answer.)
- A. Create two separate VLANs to connect the Tier-0 gateway upstream traffic and configure ECMP.
- B. Deploy a Tier-1 gateway and connect it to an Active/Active Tier-0 gateway with ECMP configured.
- C. Deploy an Active/Standby Tier-0 gateway and configure ECMP.
- D. Deploy an Active/Active Tier-0 gateway and configure ECMP.
Answer: C
NEW QUESTION # 25
A telecom company has purchased NSX-T as part of a Software Defined Data Center (SDDC) initiative. The company wants to ensure the highest performance for network traffic leaving the virtual environment.
- A. Set "Latency Sensitive" option to High when deploying the virtual NSX Edges.
- B. Use bare metal NSX Edges.
- C. Select Network cards that support VXLAN Offload.
- D. Configure SR-IOV for the virtual NSX Edges.
- E. Configure Equal-Cost Multi-Pathing on the NSX Edges.
Answer: A,D
NEW QUESTION # 26
A telecom company has purchased NSX-T as part of a Software Defined Data Center (SDDC) initiative. The company wants to ensure the highest performance for network traffic leaving the virtual environment.
Which two selections would an architect recommend to achieve the customer's goal? (Choose two.)
- A. Set "Latency Sensitive" option to High when deploying the virtual NSX Edges.
- B. Use bare metal NSX Edges.
- C. Select Network cards that support VXLAN Offload.
- D. Configure SR-IOV for the virtual NSX Edges.
- E. Configure Equal-Cost Multi-Pathing on the NSX Edges.
Answer: A,D
NEW QUESTION # 27
An NSX-T architect is working with a customer who wants to improve performance and future-proof their workloads with a multi-site architecture.
A current-state analysis captured this information:
Latency between sites is 160ms.
Bandwidth is 2Gbps.
The MTU is 1600.
What two VMware design recommendations should the architect recommend to the organization to achieve future-proofing? (Choose two.)
- A. Latency must be less than 150ms.
- B. MTU must be at least 1700.
- C. MTU is recommended to be 9000.
- D. Latency RTT is acceptable.
- E. Bandwidth must be at least 10Gbps.
Answer: A,C
Explanation:
As per VMware documentation: https://docs.vmware.com/en/VMware-NSX-T-Data-Center/3.0/administration/GUID-5D7E3D43-6497-4273-99C1-77613C36AD75.html Requirements for Multisite Deployments The bandwidth must be at least 1 Gbps and the latency (RTT) must be less than 150 ms.
MTU must be at least 1600. 9000 is recommended.
Requirements for Multisite Deployments
Inter-site Communication
- The bandwidth must be at least 1 Gbps and the latency (RTT) must be less than 150 ms.
- MTU must be at least 1600. 9000 is recommended.
NSX Manager Configuration
- Automatic backup when NSX-T Data Center configuration changes must be enabled.
- NSX Manager must be set up to use FQDN.
Data Plane Recovery
- The same internet provider must be used if public IP addresses are exposed through services such as NAT or load balancer.
- The HA mode for the tier-0 gateway must be active-standby, and the failover mode must be preemptive.
Cloud Management System
- The cloud management system (CMS) must support an NSX-T Data Center plug-in. In this release, VMware Integrated OpenStack (VIO) and vRealize Automation (vRA) satisfy this requirement.
https://docs.vmware.com/en/VMware-NSX-T-Data-Center/3.0/administration/GUID-5D7E3D43-6497-4273-99C1-77613C36AD75.html
NEW QUESTION # 28
A Solution Architect will be deploying an Ethernet Virtual Private Network (EVPN) in their NSX-T Data Center environment.
What two selections must be prepared for the EVPN deployment? (Choose two.)
- A. deployed Load Balancer
- B. remote gateway with support for IGP and VLAN priority
- C. deployed Tier-1 gateway
- D. remote gateway with support for MP-BGP and VXLAN
- E. deployed Tier-0 gateway
Answer: A,D
Explanation:
Explanation/Reference: https://docs.vmware.com/en/VMware-NSX-T-Data-Center/3.0/nsxt_30_admin.pdf
NEW QUESTION # 29
Which two VMware recommendations should an architect follow when configuring top of rack (ToR) switches in an NSX-T Data Center environment? (Choose two.)
- A. Use only IPv4 addressing in all deployments.
- B. Configure redundant physical switches to enhance availability.
- C. Configure switch ports that connect to ESXi host manually as trunk ports.
- D. Modify the Spanning Tree Protocol to increase the time to transition to the forwarding state.
- E. Configure switch ports with a Dynamic Trunking Protocol.
Answer: B,C
Explanation:
Top of Rack Physical Switches
When configuring top of rack (ToR) switches, consider the following best practices:
- Configure redundant physical switches to enhance availability.
- Configure switch ports that connect to ESXi hosts manually as trunk ports. Virtual switches are passive devices and do not support trunking protocols, such as Dynamic Trunking Protocol (DTP).
- Modify the Spanning Tree Protocol (STP) on any port that is connected to an ESXi NIC to reduce the time to transition ports over to the forwarding state, for example using the Trunk PortFast feature found in a Cisco physical switch.
- Provide DHCP or DHCP Helper capabilities on all VLANs used by TEP VMkernel ports. This setup simplifies the configuration by using DHCP to assign IP address based on the IP subnet in use.
- Configure jumbo frames on all switch ports, inter-switch link (ISL), and switched virtual interfaces (SVIs).
https://docs.vmware.com/en/VMware-Validated-Design/5.0.1/vmware-validated-design-501-sddc-nsxt-workload-architecture-design.pdf
NEW QUESTION # 30
An architect is helping an organization with the Logical Design of an NSX-T Data Center solution. This information was gathered during the Assessment Phase:
Customer currently has a single 10 host vSphere cluster.
Customer wants to improve network security and automation.
Current cluster utilization and business policies prevent changing the existing vSphere deployment.
High-availability is important to the customer.
Which three selections should the architect include in their design? (Choose three.)
- A. Remove vSphere DRS VM-Host affinity rules to the NSX-T Controller VMs.
- B. Deploy at least two NSX-T Edge virtual machines in the vSphere cluster.
- C. Apply vSphere Distributed Resource Scheduler (vSphere DRS) VM-Host anti-affinity rules to NSX Managers.
- D. Apply vSphere DRS VM-Host anti-affinity rules to the virtual machines of the NSX-T Edge cluster.
- E. Remove 2 hosts from the cluster and create a new edge cluster.
- F. Deploy the NSX Controllers in the management cluster.
Answer: B,C,D
NEW QUESTION # 31
An architect is helping an organization with the Logical Design of an NSX-T Data Center solution.
This information was gathered during the assessment:
There must be a performance based SLA for East - West traffic.
Which two key performance features should the architect recommend? (Choose two.)
- A. Enable GENEVE Offload
- B. Install advanced Edge pNIC Features
- C. Configure N-VDS enhanced Data Path
- D. Setup RSS to leverage multiple cores
- E. Leverage DPDK drivers
Answer: A,D
Explanation:
https://www.virtualizationhowto.com/2019/10/vmware-nsx-t-performance-tips-and-tuning/
NEW QUESTION # 32
Which is a family of solutions for data center designs that span compute, storage, networking, and management, serving as a blueprint for a customer's Software Defined Data Center (SDDC) implementations? (Choose the best answer.)
- A. VMware Cloud Foundation
- B. VMware SDDC Design
- C. VMware POC Design
- D. VMware Validated Design
Answer: D
NEW QUESTION # 33
Refer to the exhibits.
Design Option1:
Design Option 2:
Design Option 3:
Design Option 4:
An architect is helping an organization with the Conceptual Design of an NSX-T Data Center solution.
The conceptual design includes these requirements, assumptions, constraints, and risks:
Critical applications must run across sites without changing IP address.
Business continuity and disaster recovery (BCDR) plans will leverage a second site running vSphere.
RTO/RPO must be reduced for recovery of applications on secondary site.
IT Teams require automation tools for configuration.
Which Conceptual Design would the architect recommend to the customer? (Choose the best answer.)
- A. Design Option 1
- B. Design Option 4
- C. Design Option 3
- D. Design Option 2
Answer: D
NEW QUESTION # 34
An architect is helping an organization with the Logical Design of an NSX-T Data Center solution. This information was gathered during the Assessment Phase:
Customer is concerned with NSX Manager availability.
3 cabinets/racks are available in the data center.
No integration with 3rd party solution is required.
There is no budget for physical equipment acquisition.
The 3 cabinets/racks do not share the same L2 domain.
Which three selections should the architect include in their design to address the customer's concern with NSX Manager availability? (Choose three.)
- A. Use another NSX Manager IP in case an appliance fails.
- B. Deploy an NSX Manager Appliance per rack and cluster them.
- C. Use a physical/internal load-balancer with the cluster.
- D. Deploy a single active NSX Manager appliance in rack 1.
- E. Deploy 2 cold standby NSX Manager appliances in rack 2/3.
- F. Use separate IP per NSX Manager appliance per rack.
Answer: B,C,F
Explanation:
https://docs.vmware.com/en/VMware-NSX-T-Data-Center/2.4/installation/GUID-72A55651-0031-43A4-9F23-5950C1AFF304.html
https://vxplanet.com/2020/03/26/using-nsx-t-loadbalancer-for-the-nsx-t-management-cluster-part-1/
https://vxplanet.com/2020/03/26/using-nsx-t-loadbalancer-for-the-nsx-t-management-cluster-part-2/
NEW QUESTION # 35
An architect is helping an organization with the Logical Design of an NSX-T Data Center solution.
This information was gathered during the Assessment Phase:
There is a performance based SLA for East - West traffic.
The business critical applications require prioritization of their traffic.
One of the services is a file share and has a high demand for bandwidth.
Which selection should the architect include in their design? (Choose the best answer.)
- A. Monitor East-West traffic throughout normal business cycles.
- B. Review average North/South traffic from the core switches and firewall.
- C. Meet with the organization's application team to get additional information.
- D. Include a segment QoS profile and review the impact of utilizing this feature.
Answer: D
NEW QUESTION # 36
......
What is the cost of Advanced Design VMware NSX-T Data Center 3.0
The cost of Advanced Design VMware NSX-T Data Center 3.0 is $450.
- Passing Score: 300
- Number of Questions: 57
- Length of Examination: 105 minutes
- Format: Multiple choices, multiple answers
To prepare for the VMware 3V0-42.20 exam, candidates are recommended to have a strong understanding of VMware NSX-T Data Center technology and concepts. They should also have hands-on experience designing and implementing NSX-T Data Center solutions. VMware offers a variety of training courses and certification programs that can help candidates prepare for this exam.
Advanced Design VMware NSX-T Data Center Practice Tests 2023 | Pass 3V0-42.20 with confidence!: https://drive.google.com/open?id=1vclMyzMBx6dWTH_kWfH5Mqfi59Qmw9N9
Online Exam Practice Tests with detailed explanations!: https://www.premiumvcedump.com/VMware/valid-3V0-42.20-premium-vce-exam-dumps.html