NEW QUESTION 33
Which statement is an appropriate entry for the outline Business Case heading within the Project Brief?

  • A. 10-year service contract should be agreed with the selected service provider.
  • B. The project will run for two years and the benefits will be realized over 1a years.
  • C. External consultants were employed to conduct a feasibility study to identify the options, their likely costs and benefits.
  • D. The project should be split into four management stages.

Answer: B

 

NEW QUESTION 34
Scenario
Extract from the Project Product Description (with errors)

Which 2 statements apply to the Composition section?

  • A. Delete entry 3 because this is NOT a major product to be delivered by this project.
  • B. Amend entry 2 to 'Selected paper'.
  • C. Add 'Calendars distributed to customers'.
  • D. Delete entry 7 because these will be produced by the photographer.
  • E. Move entry 6 to Derivation because this product already exists.

Answer: A,B

 

NEW QUESTION 35
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered.
ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:

End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
During stage 3, project costs are increasing but there will still be a positive return on investment, as documented in the business case. However, corporate management has recently revised its targets for return on investment and has decided to stop the project as it will not meet the new targets.
Is this an appropriate application of the 'continued business justification' principle?

  • A. Yes, because a change in a project's justification should trigger premature closure.
  • B. No, because changes in corporate strategy should not impact a project once authorized.
  • C. No, because the project business case still justifies a project.
  • D. Yes, because changes in corporate strategy may impact a project's justification.

Answer: C

 

NEW QUESTION 36
Which of the following statements would NOT be included in the Project Product Description?

  • A. Purpose of the product
  • B. Composition
  • C. Project level tolerances
  • D. Quality criteria

Answer: D

Explanation:
Explanation/Reference:

 

NEW QUESTION 37
ABC Company has a number of projects in progress. The executive of the Health and Safety Training Project is also a member of the project board for two other projects and is very busy. As a result, during this initiation stage, the executive has appointed another person to carry out both their business assurance and the role of change authority for minor and medium severity issues.
Is this appropriate, and why?

  • A. No, because the project manager identifies the level of tailoring that is relevant for the project.
  • B. Yes, because projects that are likely to have many changes should delegate the change authority.
  • C. Yes, because people with delegated project assurance roles may act as the change authority.
  • D. No, because the decision to have a change authority should be made before the project is authorized.

Answer: C

 

NEW QUESTION 38
Scenario
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.
No Benefits Review Plan has been developed. Where should the schedule of benefit reviews be recorded?

  • A. As deliverables of the project, all benefit reviews should be scheduled and documented in the Project Plan during initiation.
  • B. Small projects do not require a schedule of benefit reviews as only one review is required towards the end of the project and this should be documented within the Business Case.
  • C. Benefit reviews should be planned and recorded in the simple PID.

Answer: C

 

NEW QUESTION 39
Use the 'Additional Information' in the Scenario Booklet to answer this question.
The Operations Director is the executive for the project and has proposed that a senior course developer be appointed as project manager. The course developer works in the Training Development Manager's team and has a good understanding of the standard course development model. The course developer was a team manager on a previous project for which the Operations Director was the executive.
Is this proposed appointment appropriate, and why?

  • A. No, because there is a conflict of interest as the Training Development Manager is responsible for gaining accreditation.
  • B. No, because the course developer's team reports to the Business Development Director, not the Operations Director.
  • C. Yes, because the course developer is likely to have the project management and specialist knowledge required.
  • D. Yes, because the course developer is responsible for ensuring that trainers deliver courses to the required standard.

Answer: D

 

NEW QUESTION 40
Scenario
Extract from the Project Product Description (with errors)

Which 2 statements apply to the Composition section?

  • A. Delete entry 3 because this is NOT a major product to be delivered by this project.
  • B. Amend entry 2 to 'Selected paper'.
  • C. Add 'Calendars distributed to customers'.
  • D. Delete entry 7 because these will be produced by the photographer.
  • E. Move entry 6 to Derivation because this product already exists.

Answer: A,B

 

NEW QUESTION 41
Scenario
Additional Information
Product Description

Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors) Introduction
1. This document defines the approach to be taken to achieve the required quality levels during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
The service level agreement contains a number of technical terms that are missing from its glossary of terms.

  • A. Raise an issue (off-specification).
  • B. No action required.
  • C. Raise an issue (request for change).
  • D. Obtain agreement from the Director of Facilities Division to add these into the glossary of terms within the remaining +2 days' tolerance.

Answer: D

 

NEW QUESTION 42
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered.
ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:

End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
ABC Company uses a standard development model to develop courses and uses PRINCE2 to manage these projects. The objectives from the Health and Safety Training Project have been documented in the business plan of ABC Company. This business plan has triggered this project. As a result, to save time, the executive has decided to simplify the 'starting up a project' process. The project mandate will be adapted and becomes the project brief.
Is this appropriate, and why?

  • A. Yes, because the executive can initiate the project based on the project mandate by passing the 'starting up a project' process.
  • B. No, because the project brief should be a statement which includes a fuller description of the project.
  • C. Yes, because the business outcomes are clear, the project brief can be a sample statement elaborating the mandate.
  • D. No, because capturing lessons from previous projects identify lessons to be applied to this project.

Answer: B

 

NEW QUESTION 43
If the Project Board are too busy to authorize all change requests themselves they can appoint?

  • A. A Change Committee
  • B. A Change Board
  • C. A Change Budget
  • D. A Change Authority

Answer: A

 

NEW QUESTION 44
Which is a correctly defined acceptance criterion for the service level agreement (SLA) with the selected service provider?

  • A. The SLA must extend for the full duration of the service contract.
  • B. The selected service provider should be located locally.
  • C. External consultants are to assist in the creation of the SLA.
  • D. Any changes to the SLA must be managed through formal change control.

Answer: A

 

NEW QUESTION 45
It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.
There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.
Which product should show that the staff photo sessions were disruptive to the Engineering Department as they had been scheduled during peak work times without consultation with the Engineering Manager?

  • A. Follow-on action recommendations
  • B. Project closure notification
  • C. Lessons Report
  • D. Risk Register

Answer: C

 

NEW QUESTION 46
Scenario
Additional Information
During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes:
There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff have not been recruited due to the reduced operation. If the project is successful, a recruitment campaign will be required to fill the existing staff vacancies and there may be a requirement for additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult to find.
In financial terms, there were a total of 1,500 orders in the last financial year, each with an average profit of
£2k. The Marketing department believes that sending a promotional calendar to our current and prospective customers would increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months from the date of distribution.
The Marketing Director will be funding the project from the business marketing budget. She believes that the effect of a good company image portrayed by a successful calendar would last into a second year. She has forecast the same increase in orders for a second year and predicts that the annual employee satisfaction survey will show a measurable improvement in staff morale.
A number of alternatives were explored, including:
20% discount for all repeat customers - not cost-effective and very short term

A promotional calendar as a free Christmas gift - would target current and prospective customers and

the benefits would last into a second year
A series of television and press advertisements was too expensive

A direct mail shot to all customers - benefit would be short term

Creation of an internet website - would not suit all customers

The calendar is seen as the favored option, as long as the company's competitors do not increase their marketing activity. Whilst the Marketing department wants a very high quality, glossy product, the project management team must be aware of the cost this will incur.
Which 2 statements should be recorded under the Timescale heading?

  • A. The print company requires a 2 week notification period of the calendar pack delivery.
  • B. The prepared calendar pack must be delivered by the first week in December.
  • C. Additional 10% increase in orders in year two.
  • D. Benefits will be lost if the project is not completed on time.
  • E. A recruitment campaign to fill the existing staff vacancies will need to take place in the next 12 months.

Answer: B,C

 

NEW QUESTION 47
Although it is not specified in the current corporate branding standards, the MFH corporate logo should be shown on the front page of the service level agreement.

  • A. Obtain agreement from the Director of Facilities Division to amend this within the remaining +2 days tolerance.
  • B. Raise an issue (request for change).
  • C. Raise an issue (off-specification).
  • D. Accept this error as a concession.

Answer: B

Explanation:
Explanation/Reference:

 

NEW QUESTION 48
Scenario:
Techniques, processes and procedures
1. Any threat that may result in a loss of MFH data must be escalated immediately.
Joint agreements
2.Work is to start at the beginning of week 2 (Stage 4).
3.The project will take two years to complete, at an estimated cost of (GBP)2.5m. Tolerances
4.None.
Constraints
5.MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
6.Installation work must take place during MFH normal working hours.
7.+(GBP)10,000 / -(GBP)25,000.
Reporting arrangements
8.Highlight Report every Monday by 10.00 am.
9.The report must contain a summary of all products worked on during the previous week.
10.
Project Manager must be notified of any issues immediately by telephone.
Problem handling and escalation
11. Impact analysis of all issues must be completed within 24 hours.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.
Approval method
13. Project Assurance will review the completed Work Package and confirm completion
Which 2 statements apply to either the Reporting arrangements or Problem handling and escalation sections?

  • A. Move entry 10 to Problem handling and escalation because that section describes how issues are handled.
  • B. Delete entry 11 because the impact analysis should be provided when the issue is notified.
  • C. Delete entry 9 because this level of detail is unnecessary.
  • D. Add 'Any risks identified to be added to the Risk Register' to Reporting arrangements.
  • E. Replace entry 8 with 'Checkpoint Report every Monday by 10.00 am' because Highlight Reports are intended for the Project Board.

Answer: B,D

 